2,600+ GW
of clean power projects in US interconnection queues
20%
of US electricity from nuclear, the largest clean baseload source
projected grid storage capacity growth by 2030
$10T+
energy transition investment by 2050 (BloombergNEF)
Today

Latest news

All news →
Utility Dive interconnectionai-demand

FERC clears PJM fast-track for 250 MW shovel-ready generation

FERC approved PJM's Expedited Interconnection Track on June 9, opening a narrow lane for up to ten 250 MW-plus projects per year that can come online within three years. The carveout sits next to the still-pending large-load rule and tilts the queue toward state-backed incumbents.

pv magazine USA, June 10 reporting on DoD restricted-parties update feocus-supply

Pentagon 1260H list adds JA Solar, Trina, EVE, CALB as DoD contracting ban begins

The Department of War published its expanded Section 1260H list of Chinese military companies on June 8, growing the roster from roughly 130 to 188 entities and pulling in solar majors JA Solar and Trina Solar alongside battery cell makers EVE Energy and CALB. The direct DoD contracting ban under the FY2024 NDAA takes effect at the end of June, with the indirect (third-party) prohibition layering in twelve months later. The action does not block commercial sales into the US market, but it formalizes a federal-procurement bright line that compounds with IRA Prohibited Foreign Entity rules and tilts US-strategic offtake further toward non-Chinese cells and modules.

Stoel Rives, OBBBA tax-credit summary irathesis-confirm

Storage ITC keeps both safe-harbor paths as solar window closes

The One Big Beautiful Bill Act left battery storage with the qualification flexibility it stripped from solar and wind. Standalone storage retains both the physical-work test and the 5 percent cost safe-harbor at any project size, and the Section 48E phase-out timeline that pins solar and wind to a 2027 placed-in-service backstop does not apply to energy storage technology. Storage developers now have a structurally easier path to credit certainty than solar developers racing the July 5 begun-construction deadline.

Holland & Knight interconnectiondata-centers

FERC's June deadline on large-load interconnection rules enters its decision window

FERC committed in April to act by the end of June on Docket RM26-4-000, the rulemaking covering how 20-MW-plus loads, mostly AI data centers, attach to the transmission system. The Commission's June 18 open meeting is now the most likely venue, with a Sunshine Notice due no later than June 11 under the seven-day rule.

pv magazine USA solarstorage

Solar and storage took 93% of new US grid capacity in Q1 2026

American Clean Power's Q1 2026 quarterly report shows utility-scale solar and battery storage absorbing nearly all new grid additions, while wind installs continue to slide. Texas is on track to be the first state past 100 GW of clean capacity, and California led storage adds with 1.1 GW.

Energy-Storage.News thesis-riskchina

Sodium-ion crosses a commercial threshold: CATL and HyperStrong sign 60 GWh BESS supply deal

China's largest battery maker has agreed to supply 60 GWh of sodium-ion cells to its largest BESS integrator, the first commercial-scale offtake commitment for the chemistry. The deal does not unseat lithium iron phosphate in 2026 at roughly $70/kWh versus $40 to $50/kWh for LFP, but it is the manufacturing scale signal sodium-ion needed. Treat it as a thesis-risk data point for the lithium supply chain, not a regime change.

Analysis

Recent long-form

All analysis →
High-voltage transmission lines and substation infrastructure at dusk
thesisferc

FERC Order 2023 cluster studies, two years in: the queue is shorter, the withdrawals are larger, and the projects that survive are not the ones the pre-reform queue prioritized.

Order 2023 transitioned interconnection studies from first-come-first-served serial review to first-ready-first-served cluster review, with deposits, commercial readiness criteria, and withdrawal penalties. PJM, MISO, CAISO, ISO-NE, NYISO, and SPP have now run at least one full cluster cycle under the reformed rules. The headline result is a sharper queue, not a faster queue. The mix of projects clearing studies has shifted toward storage, hybrid storage-plus-solar, and load-paired generation. The pure-merchant solar queue has thinned. Whether the reformed process actually accelerates clean firm capacity onto the grid depends on the next cluster, not this one.

Drilling rig at sunset against arid mountain landscape, similar to southwest Utah geothermal sites
thesisgeothermal

Enhanced geothermal is the 2030 to 2032 lever, not the 2027 to 2029 lever. Fervo Cape Station is the test case.

Fervo Energy's Cape Station in southwest Utah is the first commercial-scale enhanced geothermal project to put steel in the ground in the US. The first 90 MW phase targets 2026 commissioning, with 400 MW total by 2028. The drilling cost reductions Fervo has demonstrated are real and large. They are not large enough to make EGS a 2027 to 2029 reliability story. They make it a 2030 to 2032 story, with the size of the role determined by the next 18 months of well results and the speed of the second-mover ramp behind Fervo.

Industrial gas turbine assembly hall with large rotor sections under overhead crane
thesisgas-turbines

The binding constraint on the 2027 to 2029 reliability window is no longer interconnection studies. It is the gas turbine OEMs.

Heavy-duty gas turbine orders at GE Vernova, Siemens Energy, and Mitsubishi Heavy Industries have pushed delivery slots past 2029 for new bookings. The procurement queue, not the interconnection queue, is now the slowest piece of the reliability stack. Utilities chasing the data center load are paying reservation fees on equipment they will not see until 2030. Capacity auctions are pricing the gap.

Frequently asked

Why not just read general energy news?

Because generalist coverage buries the supply-chain and policy texture. A permitting decision on a transmission project, a DOE loan commitment to a lithium refinery, an NRC licensing milestone for an SMR, a FERC rulemaking on interconnection reform: these move capital in ways that earnings coverage misses. Clean Power Press is built for the people who track those signals.

Is this for traders or long-horizon investors?

Long-horizon. The thesis is a multi-decade buildout. The daily briefs work for tactical positioning, but the analytical frame is structural: supply-chain, policy, project-pipeline. If you're trading micro-moves on spot prices, this isn't your tool.

What verticals do you cover and how do they connect?

Energy storage and lithium, solar, nuclear and SMRs, grid and transmission, and critical minerals. Climate policy is the connective tissue. The verticals are separate editorial frames but they share a common insight: the bottleneck on every one of them is permitting, supply-chain concentration, and policy implementation, not the underlying technology.

What's your stance on climate change?

Climate change is established science. We don't give false balance to fossil-fuel-industry framing on the science. Our editorial stance is climate-forward: the clean energy transition is necessary, urgent, and one of the most consequential investment stories of the next several decades. That's not advocacy. We report facts, cover setbacks as well as progress, and don't oversell the pace of transition.

What's your analytical frame across verticals?

Track marginal, watch policy, ignore most price noise. The marginal capex dollar, the marginal project entering permitting, the marginal regulatory decision: these are where the structural story moves. Average inventory levels, spot price tapes, and quarterly headlines follow later and with lower signal value.

Get the brief

The weekly Clean Power Press brief.

One Sunday email, ~10 minutes to read. The week's signal-to-noise picks across energy storage, solar, nuclear, and clean power policy. What moved, what changes positioning, what's worth doing about it.

Subscribe

Join the early list

Drop your email. First issue lands when we hit a content cadence we trust.